Pier Project Timeline and Milestones
Project Delivery Timeline
Scheduled Highlights:
- December 2025 to June 2026: Mobilize, Vehicle Ramp
- February 2026 to June 2026: Temporary Pedestrian Bridge
- June 2026 to September 2026: Demolition
- July 2026 to December 2026: Foundations/Piles
- October 2026 to August 2027: New Bridge
- June 2027 to September 2027: Clean Up, Restore Parking Lot
- December 2027: Project Complete
Construction is expected to begin in late-2025 and will take approximately two years. Please note, construction is dependent on many variables, including weather, and this schedule information is therefore subject to change.