Appian Way reopens ahead of schedule following accelerated Pier Bridge demolition

July 28, 2026 1:42 PM

SANTA MONICA, Calif. (July 28, 2026) —  Appian Way reopened Tuesday to vehicle traffic days ahead of schedule, restoring the primary access route to the main Pier parking lots.

As part of the Santa Monica Pier Bridge Replacement Project, Appian Way was anticipated to remain closed for up to eight days while crews demolished a portion of the existing Pier Bridge over the roadway. Thanks to an innovative alternative construction approach, demolition was completed significantly ahead of schedule, allowing the roadway to reopen after just one day.

Rather than using the saw-cutting method employed in other areas of the bridge, the contractor utilized two hydraulic breakers to complete demolition in this section. This approach substantially accelerated construction activities while maintaining safety, allowing crews to restore access much sooner than originally anticipated.

The Santa Monica Pier Bridge Replacement Project will continue to improve the safety, accessibility and long-term reliability of this historic gateway while maintaining access to the Pier and its businesses. The project is scheduled to be completed by 2028, in time for the Olympic and Paralympic Games in Los Angeles.

For the latest project updates, visit santamonica.gov/pierbridge.

Media Contact

Lauren Howland
Communications and public information manager
lauren.howland@santamonica.gov

Categories

Departments, Parking, Strategic Priorities, Street Closures

Departments

Public Works