Recycled Water Pipeline Project

The City of Santa Monica has contracted with Blois Construction, to install new pipeline and expand the recycled water distribution system in the City. The construction will occur on Cloverfield Boulevard from Olympic Boulevard to Santa Monica Boulevard and on Santa Monica Boulevard from Cloverfield Boulevard to 21st Street. 

Construction is anticipated to begin in September 2023 and last approximately 8 months. There will be traffic, detours, and parking impacts and the operation of heavy equipment necessary to construct this project will create intermittent loud noise. 

The initial work will consist of utility investigations in September 2023 throughout the project limits, then the construction of the new pipeline will start in October 2023 and will go through May 2024 in phases. Please note that the start and completion times/dates of the construction may change due to unforeseen conditions and weather. 

Click on the Day Work Notice to see a map of the project phases: Day Work Public Notice

The project is currently on Phase 1 which includes Main Line Installation. 

*Dates are tentative and might change due to unforeseen conditions. 

  • Phase 1: Cloverfield Blvd and Olympic Blvd Intersection - NIGHT WORK 8:00 PM to 6:00 AM - COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation – COMPLETE

        Eastbound Olympic Blvd, NO LEFT at Cloverfield Blvd

  • Phase 2: Cloverfield Blvd between Olympic Blvd and Colorado Ave - NIGHT WORK 8:00 PM to 6:00 AM - COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation – COMPLETE

  • Phase 3: Cloverfield Blvd and Colorado Ave Intersection - NIGHT WORK 8:00 PM to 6:00 AM - COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation – COMPLETE

    Street Restoration - COMPLETE

        Eastbound Colorado Ave, NO RIGHT at Cloverfield Blvd

        Eastbound Colorado Ave, NO LEFT at Cloverfield Blvd

        Northbound Cloverfield Blvd, NO LEFT at Colorado Ave

        Southbound Cloverfield Blvd, NO LEFT at Colorado Ave

  • Phase 4 : Cloverfield Blvd between Colorado Ave and Broadway- NIGHT WORK 8:00 PM to 6:00 AM COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation –  COMPLETE

    Street Restoration - COMPLETE

        Northbound Cloverfield Blvd, NO LEFT at Broadway

        Southbound Cloverfield Blvd, NO LEFT at Broadway

  • Phase 5: Cloverfield Blvd and Broadway Intersection - DAY WORK 8:00 AM to 6:00 PM COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation – COMPLETE

        Northbound Cloverfield Blvd, NO LEFT at Broadway

        Southbound Cloverfield Blvd, NO LEFT at Broadway

        Eastbound Broadway, NO LEFT at Cloverfield Blvd

        Eastbound Broadway, NO RIGHT at Cloverfield Blvd

        Westbound Broadway, NO LEFT at Cloverfield Blvd

        Southbound 23rd Street, NO LEFT at Broadway

        Southbound 24th Street, NO LEFT at Broadway

        Eastbound Broadway, BIKE LANE CLOSED – SHARE ROAD

        Westbound Broadway, BIKE LANE CLOSED – SHARE ROAD

  • Phase 6: Cloverfield Blvd between Broadway and Santa Monica Blvd - DAY WORK 8:00 AM to 6:00 PM - COMPLETE

        Utility Investigation – COMPLETE

        Main Line Installation – COMPELTE

        Westbound Schader Dr, NO LEFT at Cloverfield Blvd

        Westbound Schader Dr, NO RIGHT at Cloverfield Blvd

        Northbound Cloverfield Blvd, NO LEFT at Broadway

        Southbound Cloverfield Blvd, NO LEFT at Broadway

  • Phase 7: Cloverfield Blvd and Santa Monica Blvd Intersection - NIGHT WORK 8:00 PM to 6:00 AM

        Utility Investigation – COMPLETE

        Main Line Installation – April 8th, 2024, through April 19th, 2024

        Westbound Santa Monica Blvd, NO LEFT at Cloverfield Blvd

        Eastbound Santa Monica Blvd, NO RIGHT at Cloverfield Blvd

        Westbound Santa Monica Blvd, NO LEFT at 23rd Street

  • Phase 8: Santa Monica Blvd between Cloverfield Blvd and 21st Street - NIGHT WORK 8:00 PM to 6:00 AM

        Utility Investigation – COMPLETE

        Main Line Installation – April 22nd, 2024 through May 6th, 2024

        Southbound 23rd Street, NO LEFT at Santa Monica Blvd

        Eastbound Santa Monica Blvd, NO LEFT at 23rd Street

        Westbound Santa Monica Blvd, NO LEFT at 23rd Street

        Westbound Santa Monica Blvd, NO LEFT at 21st Street

We understand this process is inconvenient and will make every effort to minimize any inconvenience that this work may cause. Please contact the Construction Manager, at the phone number provided, if you have any specific concerns or questions. Thank you in advance for your patience and understanding.